Short answer

Sections 7 and 8 of FEMA give Indian exporters two duties. Section 7 requires exporters of goods and services to declare the export to RBI or a specified authority. Section 8 requires them to realise and bring the money into India within the period RBI sets. That period is now nine months from shipment or invoice.

What do Sections 7 and 8 of FEMA say about exports?

Section 7 of FEMA is the declaration duty and Section 8 is the realisation duty. Section 7 tells exporters to report the export and its value in the form RBI specifies. Section 8 tells every person resident in India to take all reasonable steps to bring foreign exchange owed to them into India within the period RBI specifies.

  • Goods: Every exporter of goods must furnish a declaration with true and correct material particulars, including the full export value. If the full value is not known at the time of export, the exporter declares the value it expects to receive in the market outside India (FEMA section 7(1)(a)).
  • Extra information: An exporter of goods must also give RBI any other information it needs to make sure the export proceeds are realised (FEMA section 7(1)(b)).
  • RBI directions: RBI may direct any exporter to meet requirements it thinks fit so that the full export value, or a reduced value RBI determines, is received without delay (FEMA section 7(2)).
  • Services: Every exporter of services must furnish a declaration with true and correct material particulars about payment for those services (FEMA section 7(3)).
  • Realisation: Where foreign exchange is due or has accrued to a person resident in India, that person must take all reasonable steps to realise and repatriate it to India within the period and manner RBI specifies (FEMA section 8).
  • Meaning of export: FEMA defines export as taking goods out of India to a place outside India, and providing services from India to any person outside India (FEMA section 2(l)).

The Act sets the duties in broad terms and leaves the form, period and manner to RBI. RBI fills in those details through regulations. From 1 October 2026 those details sit in the Foreign Exchange Management (Export and Import of Goods and Services) Regulations, 2026, which RBI made using its powers under Section 7, Section 8, Section 10(6) and Section 47(2) of FEMA. For a wider overview, see FEMA rules for exports.

Who must follow Sections 7 and 8 of FEMA as an exporter?

Sections 7 and 8 of FEMA apply to anyone in India who exports goods or services. The Act draws no line by business size or legal form, so a sole freelancer has the same declaration and realisation duties as a large company. The regulations set out a few exclusions and simpler routes for small invoices.

How does an exporter comply with Sections 7 and 8 of FEMA?

An exporter complies with Sections 7 and 8 of FEMA by declaring each export on the Export Declaration Form (EDF) and then receiving the full export value through an AD bank within the realisation period. The AD bank records both steps in EDPMS and closes the entry once the money arrives.

  1. Raise the invoice for the full value of the goods or services. Section 7 asks for the full export value, or the expected value for goods when the full value is not known at shipment (FEMA section 7(1)(a)).
  2. Declare the export on the EDF. For goods, this happens at the time of export, and at EDI ports the shipping bill counts as the EDF (Regulation 3(1)). For services, file within 30 days from the end of the month in which you raised the invoice (Regulation 3(2)). See EDF form for exports.
  3. Use one EDF a month if you have several service invoices. A services exporter may submit a single EDF for all exports to one or more recipients in a month (Regulation 3(2)(a)).
  4. Receive payment in the manner RBI allows. Receipts must follow the Foreign Exchange Management (Manner of Receipt and Payment) Regulations, 2023 (Regulation 4(1)).
  5. Realise the full export value within nine months from the date of shipment for goods, or from the invoice date for services (Regulation 5(1)(a)). The period is twelve months if the export is invoiced or settled in Indian rupees (Regulation 5(1), first proviso).
  6. Let the AD bank close the EDPMS entry. The bank credits your account after checking the transaction is genuine and closes or updates the EDPMS entry at the same time (Regulation 4(2)). See EDPMS closure.
  7. Ask the AD bank before the deadline if payment will be late or short. The bank may extend the period or allow a reduction in value if it is satisfied with your reasons (Regulations 5(1) and 6).

How does Section 7 of FEMA work for services exporters under the 2026 regulations?

For services, the Section 7 declaration is the EDF filed with the specified authority, which for services other than software is an AD bank in the Domestic Tariff Area (Regulation 2(1)(f)). The regulations add some flexibility.

  • A services exporter other than a software exporter may submit the EDF on or before the date it receives payment (Regulation 3(2)(b)).
  • The AD bank may extend the time to submit the EDF if you give reasons for the delay and it finds them reasonable (Regulation 3(2)(c)).
  • For software, the specified authority is an AD bank or STPI in the Domestic Tariff Area, and the Development Commissioner in an SEZ (Regulation 2(1)(f)(iii)).

How does Section 8 of FEMA treat a short payment or a payment that never arrives?

Section 8 asks you to take all reasonable steps to realise the money. The regulations give the AD bank power to accept less than the full value when you show good reasons (Regulation 6).

  • For export value up to ₹10 lakh per shipping bill or invoice, the bank may permit a reduction, including non-realisation, on your declaration.
  • Above ₹10 lakh, the bank decides on your request after checking the reasons you give.
  • See reduction in export invoice value and write-off of export bills for the details.

Can an exporter set off receivables against payables and still meet Section 8 of FEMA?

Yes. Realisation under the regulations includes set-off. The AD bank may allow export receivables to be set off against import payables with the same overseas buyer or supplier, or their overseas group or associate companies, within the realisation period or any extension (Regulations 5(1) and 7). See set-off of export receivables.

How does an advance payment fit with Sections 7 and 8 of FEMA?

An exporter who receives an advance must route the advance and any later export proceeds through the same AD bank, or tell both banks if it changes banks (Regulation 10(1)). The AD bank records advance remittances in EDPMS (Regulation 18(1)(e)). See advance payment against exports.

What are the deadlines under Sections 7 and 8 of FEMA for exporters?

The deadlines under Sections 7 and 8 of FEMA come from the 2026 regulations. The EDF is due at the time of export for goods and within 30 days from the end of the invoice month for services. Payment is due within nine months, or twelve months for rupee invoicing or settlement, unless the AD bank extends it.

What happens if an exporter breaks Section 7 or Section 8 of FEMA?

An exporter who breaks Section 7 or Section 8 of FEMA, or the regulations made under them, can be penalised after adjudication under Section 13. Exports left unrealised for more than a year past the due date also restrict how the exporter can be paid for future exports.

  • Penalty: A person who contravenes the Act or any regulation, direction or order under it is liable, upon adjudication, to a penalty up to three times the sum involved where it is quantifiable, or up to ₹2 lakh where it is not (FEMA section 13(1)).
  • Daily penalty: For a continuing contravention, a further penalty of up to ₹5,000 can apply for every day after the first day (FEMA section 13(1)).
  • Confiscation: The Adjudicating Authority may also order confiscation of the currency or property involved and direct that foreign exchange holdings be brought back into India (FEMA section 13(2)).
  • Future exports: If export proceeds stay unrealised for more than one year beyond the due date or extended date, further exports can be made only against full advance or an irrevocable Letter of Credit (Regulation 13). See export proceeds not realised.
  • Caution list: Exporters on RBI's caution list as on 30 September 2026 remain governed by the earlier order until they are removed from the list (Regulation 13, proviso). See RBI exporter caution list.
  • Compounding: A contravention under Section 13 can be compounded on application, within 180 days from receipt of the application (FEMA section 15(1)). RBI's directions set an application fee of ₹10,000 plus GST (A.P. (DIR Series) Circular No. 17 of 2024-25, para 3.2).

If an invoice is close to its deadline, ask your AD bank for an extension under Regulation 5(1) or a reduction under Regulation 6 before it lapses, with written reasons and buyer correspondence. If a breach has already happened, a compounding application can be filed with RBI (A.P. (DIR Series) Circular No. 17 of 2024-25, para 3.1). See extension of export realisation period and FEMA penalties and compounding.

Which RBI rules apply Sections 7 and 8 of FEMA to exporters?

Sections 7 and 8 of FEMA are applied to exporters through the 2026 export and import regulations and A.P. (DIR Series) Circular No. 20, both effective from 1 October 2026. Penalties and compounding come from Sections 13 and 15 of the Act and RBI's 2024 compounding directions.

What are common mistakes exporters make with Sections 7 and 8 of FEMA?

  • Size myth: Some exporters assume FEMA applies only to companies. Section 7 covers every exporter of goods and every exporter of services, with no turnover threshold in the Act (FEMA section 7).
  • Old deadlines: Older guides cite the superseded Master Direction on Export of Goods and Services. From 1 October 2026 the current deadlines are in the 2026 regulations (Circular No. 20, para 4).
  • Superseded periods: Some summaries of the 2026 regulations quote the periods as first notified in January 2026: fifteen months, or eighteen months for rupee exports. The September 2026 amendment replaced these with nine and twelve months (Regulation 5, footnotes 2 to 4).
  • Late requests: Waiting until after the deadline to ask for an extension. The AD bank may allow more time when the exporter asks and cites reasons for the delay, so raise the request with your AD bank as early as possible (Regulation 5(1), second proviso).
  • Partial value: Declaring only the amount expected after fees or discounts. Section 7 asks for the full export value, and any shortfall is handled later as a reduction through the AD bank (Regulation 6).
  • Split banks: Receiving an advance through one bank and the balance through another without telling both banks (Regulation 10(1)).

How did we verify this?

Every rule, deadline and form on this page is linked to its official source, checked on the dates below.

  1. The Foreign Exchange Management Act, 1999 (Act No. 42 of 1999), text hosted by IFSCA, Sections 2(l), 7(1), 7(2), 7(3), 8, 13(1), 13(2) and 15(1) (checked 8 Oct 2026)
  2. Foreign Exchange Management (Export and Import of Goods and Services) Regulations, 2026, Notification No. FEMA 23(R)/2026-RB dated 13 January 2026, amended up to 22 September 2026, Preamble; Regulations 1(2), 2(1), 3, 4, 5 with footnotes 2 to 4, 6, 7, 10(1), 13 with footnote 5, 18(1)(b) and (e), 19 (checked 8 Oct 2026)
  3. RBI A.P. (DIR Series) Circular No. 20, RBI/2025-26/194: Export and Import of Goods and Services, 16 January 2026, Paras 1, 4 and 7 (checked 8 Oct 2026)
  4. RBI A.P. (DIR Series) Circular No. 17, RBI/FED/2024-25/78: Directions - Compounding of Contraventions under FEMA, 1999, 1 October 2024, Covering letter; paras 1.1 to 1.3, 3.1 and 3.2 (checked 8 Oct 2026)

Frequently asked questions

Does FEMA Section 7 require a separate declaration for every service invoice?

No. Under the 2026 regulations, a services exporter who exports to one or more recipients in a month may submit a single EDF covering all those exports. The EDF is due within 30 days from the end of the month in which the invoices were raised. Your AD bank then enters it in EDPMS within five working days.

Is the nine month realisation period written into FEMA Section 8 itself?

No. Section 8 only says the money must be realised within the period and manner RBI specifies. The nine month period comes from Regulation 5 of the Foreign Exchange Management (Export and Import of Goods and Services) Regulations, 2026. RBI can change that period through regulations without Parliament amending the Act.

Can an AD bank extend the FEMA realisation deadline without going to RBI?

Yes. Regulation 5(1) lets the AD bank allow more time for realisation when the exporter asks and cites reasons for the delay, and the bank is satisfied with those reasons. Each bank must cover extensions in its internal policy and disclose that policy and the main features of its procedure on its website.

What is the maximum FEMA Section 13 penalty for an unrealised export invoice?

Section 13(1) allows a penalty of up to three times the sum involved when the amount can be quantified, or up to ₹2 lakh when it cannot. A continuing contravention can attract up to ₹5,000 for each day after the first. The penalty is imposed only after adjudication by the Adjudicating Authority.

Who can compound a FEMA contravention by an exporter, and how long does it take?

Section 15 of FEMA allows a contravention under Section 13 to be compounded on application by authorised officers of the Directorate of Enforcement or RBI. At RBI, the officers named in Rule 4 of the Foreign Exchange (Compounding Proceedings) Rules, 2024 handle applications, filed physically or through PRAVAAH. The Act sets a 180 day limit.

Do FEMA Sections 7 and 8 apply to a freelancer paid through a foreign platform?

Yes. FEMA defines export to include providing services from India to any person outside India, and Section 7(3) covers every exporter of services. The money must reach India within the period RBI specifies. Ask your AD bank how it records receipts that arrive through an intermediary.

Does the ₹10 lakh EDPMS declaration route change FEMA Section 8 duties?

No. The duty to realise the money still applies. Regulation 4(2) lets the AD bank close EDPMS entries for shipping bills or invoices up to ₹10 lakh on the exporter's declaration that payment was realised in full or otherwise. Exporters may also submit these declarations quarterly for bulk closure.